Axion Autopista Bs. As. – La Plata enters the final stretch

At the end of April, the work resumed the tasks in the Shop, leaving behind the structural stage to continue with the closings and finishes that give texture to the building. At the same time, in the Parking and Canopy sectors, the concrete runs that paint the pavement color on the land where the installations that will bring life to the service stations were resumed. To restart the activity, all the personnel were trained by the Safety and Hygiene team on the care to be taken with regard to COVID-19. All sectors of the property were disinfected and reconditioned seeking to adapt it to new needs.